Patna, Aug 17 (IANS) Bihar Rajya Pul Nirman Nigam Limited (BRPNNL) on Saturday issued a clarification regarding the under-construction Aguwani Ghat bridge, saying that the portion of the bridge which has collapsed had been previously identified as “damaged” and was already in the process of “demolition”.

BRPNNL, the bridge construction body, said that the first damage occurred on April 30, 2022, during the construction of the extra-dosed segment of the bridge.

“The faulty design of the bridge was reviewed by experts from IIT Roorkee, leading to instructions for the damaged portion to be demolished and removed. The foundation and sub-structure of the bridge were also subjected to further examination,” BRPNNL said.

BRPNNL said that despite these measures, another part of the bridge, constructed using the same technology, was damaged on June 4, 2023.

“After the faulty design was confirmed, all construction work on the bridge was immediately halted and the contractor was instructed to remove the problematic sections,” the bridge construction body said.

It also clarified that the remaining portion of the previously damaged segment, which was still in the process of being dismantled, collapsed again due to the rise in the water level and the strong flow of the Ganga River.

“This marked the third instance of damage to the bridge on Saturday,” BRPNNL said.

The Patna High Court had also ordered that the work on this section be redone entirely at the contractor’s expense. BRPNNL mentioned that the redesign of this segment is currently underway, and once approved, the construction will restart.

The collapsed structure is a 2×2 lane high-level RCC bridge being built over the Ganga River, connecting Agwani Ghat in Khagaria district and Sultanganj in Bhagalpur district.

The project was awarded under the Engineering, Procurement, and Construction (EPC), mode with the contractor bearing responsibility for the bridge’s design.

However, the bridge has now collapsed three times in the past two years, raising serious concerns about construction quality and oversight.

Sanjeev Kumar, a JD-U MLA representing the Parbatta Assembly constituency – which includes Agwani Ghat – expressed grave concerns about the bridge’s construction quality.

“I previously raised these issues in the Assembly and also met Chief Minister Nitish Kumar. The repeated collapses over the last two years are a matter of serious concern and reflect poorly on the state’s infrastructure management,” Kumar said.

The incident has intensified criticism of the Nitish Kumar government, with opposition leaders, including Tejashwi Yadav, seizing the opportunity to highlight failures and corruption within the system.

Sanjeev Kumar’s criticism from within the ruling party underscores the growing dissatisfaction and highlights the severity of the situation.

–IANS

ajk/dan

Go to Source

Disclaimer

The information contained in this website is for general information purposes only. The information is provided by TodayIndia.news and while we endeavour to keep the information up to date and correct, we make no representations or warranties of any kind, express or implied, about the completeness, accuracy, reliability, suitability or availability with respect to the website or the information, products, services, or related graphics contained on the website for any purpose. Any reliance you place on such information is therefore strictly at your own risk.

In no event will we be liable for any loss or damage including without limitation, indirect or consequential loss or damage, or any loss or damage whatsoever arising from loss of data or profits arising out of, or in connection with, the use of this website.

Through this website you are able to link to other websites which are not under the control of TodayIndia.news We have no control over the nature, content and availability of those sites. The inclusion of any links does not necessarily imply a recommendation or endorse the views expressed within them.

Every effort is made to keep the website up and running smoothly. However, TodayIndia.news takes no responsibility for, and will not be liable for, the website being temporarily unavailable due to technical issues beyond our control.

For any legal details or query please visit original source link given with news or click on Go to Source.

Our translation service aims to offer the most accurate translation possible and we rarely experience any issues with news post. However, as the translation is carried out by third part tool there is a possibility for error to cause the occasional inaccuracy. We therefore require you to accept this disclaimer before confirming any translation news with us.

If you are not willing to accept this disclaimer then we recommend reading news post in its original language.

RELATED ARTICLES
- Advertisment -

Most Popular