Srinagar, Nov 12 (IANS) J&K Anti Corruption Bureau (ACB) on Tuesday registered a case against a former chief engineer and others allegedly involved in corruption.
A statement by ACB said: “During the course of verification, it came to fore that tender was invited through Joint Commissioner Works/ Chief Engineer Mughal Road Project PWD (R&B) Department on 15.03.2005 and after the due procedure, the award of the contract was allotted to M/s Hindustan Construction Company Ltd. for ₹214,40,00,000 by Development Commissioner Works on the approval/ recommendation of State Contract Committee.
An agreement into this effect was entered vide Agreement No. 61 PW(R&B) of 2006, dated 06.02.2006 wherein the date of start was 01.03.2006 and the date of completion was 36 months i.e. 28.02.2009. Thereafter, the supplementary agreement drawn on 25.01.2010 has been entered into the parties for ₹126.64 crores, with the date of completion as 31.03.2011.
Extension of time was further granted with time of completion up to 15-02-2012.
As the work was not completed up to the prescribed time i.e. 15.02.2012, the company again raised the issue for grant of extension of time for delay. The matter was referred to Arbitration for settling the disputes so raised.
The verification conducted further revealed that Chief Engineer Raman Puri used to interact/meet with representatives of M/s Hindustan Construction Company Ltd outside his office without following the codal procedure with the intention of extracting undue benefit.
The then Chief Engineer in connivance with M/s Hindustan Construction Company Ltd. taking undue advantage of the prior escalation clause, signed a letter on the letterhead of the construction company, agreeing to the mutual conditions including accepting of prior escalation for the period w.e.f 15.02.2012 to 31.12.2012, which resulted in the arbitration award of ₹21.52 crore plus ₹11.27 crore in favour of Hindustan Construction Company and corresponding loss to the government exchequer.
By acting in this manner, the then Chief Engineer, Mughal Road Project PWD (R&B) Department namely Raman Puri, by abuse of his official position and in lieu of criminal conspiracy with the beneficiary company, exceeded his powers/competence and accepted the terms and conditions of Contractor M/s Hindustan Construction Company Ltd which formed the basis of the award by Arbitration tribunal dated 28.03.2019.
The undue benefit was given to the company with the extension of time for which no prior order/communication stands issued, besides prevented imposition of liquidation of damages to the tune of ₹54.00 crores on the company for its inability to complete the project in the stipulated time etc.
The facts constitute the commission of offences punishable under section 5(1) (d) r/w Section 5 (2) of J&K PC Act Svt 2006 & section 120-B of RPC against Raman Puri, then Chief Engineer, beneficiary company M/s Hindustan Construction Company Ltd. and others. Consequently, a case FIR No. 23/2024 is registered in P/S ACB Srinagar. Further investigation into the case is going on.
–IANS
sq/dan
Disclaimer
The information contained in this website is for general information purposes only. The information is provided by TodayIndia.news and while we endeavour to keep the information up to date and correct, we make no representations or warranties of any kind, express or implied, about the completeness, accuracy, reliability, suitability or availability with respect to the website or the information, products, services, or related graphics contained on the website for any purpose. Any reliance you place on such information is therefore strictly at your own risk.
In no event will we be liable for any loss or damage including without limitation, indirect or consequential loss or damage, or any loss or damage whatsoever arising from loss of data or profits arising out of, or in connection with, the use of this website.
Through this website you are able to link to other websites which are not under the control of TodayIndia.news We have no control over the nature, content and availability of those sites. The inclusion of any links does not necessarily imply a recommendation or endorse the views expressed within them.
Every effort is made to keep the website up and running smoothly. However, TodayIndia.news takes no responsibility for, and will not be liable for, the website being temporarily unavailable due to technical issues beyond our control.
For any legal details or query please visit original source link given with news or click on Go to Source.
Our translation service aims to offer the most accurate translation possible and we rarely experience any issues with news post. However, as the translation is carried out by third part tool there is a possibility for error to cause the occasional inaccuracy. We therefore require you to accept this disclaimer before confirming any translation news with us.
If you are not willing to accept this disclaimer then we recommend reading news post in its original language.